The Project:
The GNPP is a gas-fired power plant with several ancillary facilities. It is a Specific Investment Loan (SIL) approved by the Board on June 8, 2010 and financed through a Loan in the amount of $600 million. Additional fmancing was approved for the Project in the amount of $240 million on February 14, 2012. The Project Appraisal Document (PAD) states that the ''project development objective is to contribute to improving the security and efficiency of electricity supply by adding a new generation capacity based on the most efficient thermal power generation technology".
The Request:
The Requesters state they have experienced some Project-related impacts already, and fear additional impacts may arise as Project construction progresses. The Requesters concerns relate to water availability for their crops and other impacts of the Project on their agricultural land, as well as concerns about resettlement, pollution, and transparency and consultation.
Note:
Translations of Inspection Panel and Management documents are unofficial and are provided as a service to interested parties. Every effort has been made to ensure accuracy. If any part of the translation in Arabic is inconsistent with the original text in English, the latter shall govern.
ترجمة وثائق هيئة التفتيش و جهاز الإدارة غير رسمية. يتم توفيرها كخدمة للأطراف المعنية. كل الجهود قد بذلت لضمان الدقة. إذا كان أي جزء من الترجمة إلى اللغة العربية لا يتفق مع النص الأصلي باللغة الانجليزية ، فإن هذا الاخير هو الذي يحكم